Road Closures and Construction

Road construction season is underway. See the Municipal 511 map below for real-time updates or the list of projects below for road work planned this season. Please note projects may be delayed due to unforeseen circumstances, such as weather and supply chain issues. The Township asks that drivers plan their routes accordingly and obey all signs and traffic controls in work zones to ensure the safety of local workers.

You can also follow updates on significant road projects at engagefrontenac.ca. If you have any questions, contact us at 613-376-3027 or by email pwsupport@southfrontenac.net. Some projects have been funded in part by the Canada Community-Building Fund. 

Key Links

2026 Road Construction Projects

Project will include the second and final phase of reconstruction of approximately 1.8 km of Road 38 from Yarker Road to Murton Road. Recommended design will include full depth reconstruction of the roadway complete with two lanes and two paved shoulders (11.0m width) and shoulder rounding.

  • Start date: June 2026
  • End date: November 2026
  • Duration: 10-12 weeks

Traffic will be reduced to a single lane for the duration of the project. Traffic construction signs will be installed. Drivers and pedestrians are required to obey all construction signs and expect delays. This project has been funded in part by the Canada Community-Building Fund.  See the engagefrontenac.ca project page for more details and updates.

Project will include the reconstruction of approximately 2.2 km of Keeley Road from 0.3 km east of Sydenham Road to Park Valley Road. Construction to include full depth reclamation, placement of granular A, double surface treatment renewal, fog seal and culvert replacements. Project will also include roadside drainage improvements. Further details will be available on engagefrontenac.ca soon.

  • Start date: June 2026
  • End date: September 2026
  • Duration: 10-12 weeks

Traffic will be reduced to alternating single lane closures for the duration of the project. Traffic construction signs will be installed. Drivers and pedestrians are required to obey all construction signs and expect delays.

Project will include the reconstruction of the 700m section of Westport Road from Lee Road to Devil Lake. Construction to include full depth reclamation, placement of granular A materials, and renewed surface (asphalt). Project will also include roadside drainage improvements.

  • Start date: June 2026
  • End date: September 2026
  • Duration: 10-12 weeks

Traffic will be reduced to a single lane for the duration of the project. Traffic construction signs will be installed. Drivers and pedestrians are required to obey all construction signs and expect delays.

Work will begin on the rehabilitation of approximately 27 kms of surface treated roadways with localized surface repairs and application of a single surface treatment (chip seal).  These chip seals typically add 5 to 7 years of additional service life at a relatively low cost.  Rehabilitations also help lower unplanned maintenance costs (potholes, cracking and edge break up). More details will be available on engagefrontenac.ca soon. 

  • Start date: June 2026
  • End date: October 2026
  • Duration: 8-10 weeks

Traffic will be reduced to a single lane and traffic signs will be installed. Drivers and pedestrians are required to obey all construction signs and expect delays.

The Bedford Mills Bridge is located on Perth Road approximately 0.3 km north of Massassauga Road. The bridge structure was built in 1962 and first rehabilitated back in 1997. The bridge is a single span T-Beam Structure with a deck slab system. The bridge has an overall span of 19.1m and a width of 9.9m.

The bridge structure is currently recommended for rehabilitation work on the abutments, pre-stressed girders, (new) concrete approach slabs and distribution slabs,  expansion joints,  bearing seats, barrier systems,  guiderail systems, and erosion at embankments. 

  • Start date: July 2026
  • End date: October 2026
  • Duration: 10-12 weeks

Traffic crossing the bridge will be limited to a single lane for the duration of the project. This project has been funded in part by the Canada Community Building Fund (CCBF).

The Eagle Creek bridge structure is located on Bob's Lake Road approximately 2.2 km north of Buck Bay Road. The existing rigid frame concrete structure which was constructed in the 1940’s has a span of 5.4 m and a deck width of 3.9 m (single lane). The bridge structure is recommended to be replaced with a wider 2 lane bridge structure complete with upgraded traffic approaches and roadside barrier systems.  See the engagefrontenac.ca project page for more details and updates.

  • Start date: July 2026
  • End date: October 2026
  • Duration: 10-12 weeks

There will be a two-way road closure during the duration of the bridge closure. Road detour signs and traffic construction signs will be installed in advance of the project. This project has been funded in part by the Canada Community Building Fund (CCBF).

Project will include the reconstruction of approximately 2.95 km of Desert Lake Road from Road 38 to 0.15 km West of High Falls Road. Construction to include full depth reclamation, placement of Granular A, double surface treatment (chip seal), fog seal,  guide rail replacements and culvert replacements. Project will also include roadside drainage improvements. See the engagefrontenac.ca project page for more details and updates.

  • Start date: June 2026
  • End date: September 2026
  • Duration: 10-12 weeks

Traffic will be reduced to alternating single lane closures for the duration of the project. Traffic construction signs will be installed. Drivers and pedestrians are required to obey all construction signs and expect delays. This project has been funded in part by the Canada Community Building Fund (CCBF) and the Ontario Community Infrastructure Fund (OCIF).

Project will include the reconstruction of approximately 2.0 km of Round Lake Road from Latimer Road to Duff Road. Construction to include full depth reclamation, placement of granular A, double surface treatment (chip seal), fog seal and culvert replacements. Project will also include roadside drainage improvements.

  • Start date: June 2026
  • End date: September 2026
  • Duration: 10-12 weeks

Traffic will be reduced to alternating single lane closures for the duration of the project. Traffic construction signs will be installed. Drivers and pedestrians are required to obey all construction signs and expect delays.

Reconstruction project will include the 5.5 km gravel section of Canoe Lake Road to 3 km south of Westport Road. Activities to include extensive rock ditching, rock cut removals (roadside hazards) localized widenings (hills/corners) and placement of new gravel wear surface (100mm) and granular M.   

  • Start date: June 2026
  • End date: September 2026
  • Duration: 10-12 weeks

Traffic will be reduced to alternating single lane closures for the duration of the project. Traffic construction signs will be installed. Drivers and pedestrians are required to obey all construction signs and expect delays. 

Temporary Road Closure Request

If your organization is planning a special event that requires the temporary closure of a road or a portion thereof, please complete the Temporary Road Closure Request form and submit it the Manager of Operations & Fleet for review. If you have any questions about this process, contact our Public Services Department at (613) 376-3027.